---
title: "Cooling Water Treatment — Donglin Controls"
description: "Starting with the client’s outlet-water requirements, EFMC coordinated process engineering, electrical automation, civil and piping works, data-center-side interfaces, construction and commissioning as one turnkey cooling-water treatment project."
canonical: https://efmc-automation.com/en/cases/ai-data-center-cooling-water-treatment-turnkey
language: en
---
![Completed cooling-water treatment workshop for an AI data center](/api/media/file/%E5%AE%8C%E5%B7%A5%E7%85%A7%E7%89%87-%E8%BD%A6%E9%97%B41.webp)

Water Treatment

# Cooling Water Treatment for an AI data center.

Starting with the client’s outlet-water requirements, EFMC coordinated process engineering, electrical automation, civil and piping works, data-center-side interfaces, construction and commissioning as one turnkey cooling-water treatment project.

Water-quality-led designUF + RO processElectrical automationTurnkey integration

IndustryWater Treatment

12

Design water-quality indicators

4 disciplines

Integrated engineering scope

01

Client requirement

## The project began with water quality, but it could not end with process equipment alone.

The client needed a complete cooling-water treatment system for an AI compute facility. The treatment process had to meet the specified outlet-water criteria and connect cleanly with power, controls, buildings, pipelines and the operating data center.

**01**

### A defined water-quality basis

Twelve client-provided indicators established the design basis, covering pH, turbidity, conductivity, hardness, alkalinity, chloride, iron, sulfate, ammonia nitrogen, COD, bacteria and organic phosphorus.

**02**

### Several disciplines, one interface

Process design, electrical automation, civil works and piping could not be developed as isolated packages; equipment footprints, utilities, signals and tie-in points had to agree before construction.

**03**

### A system ready to operate

The required endpoint was not separate skids or drawings. It was an integrated installation that could be commissioned, monitored from the supervisory system and handed over as a working plant.

02

Design basis

## Client water-quality criteria became engineering inputs, not a note added after design.

The supplied outlet-water schedule defined twelve parameters. The values below are selected design criteria from that schedule, not claims of field-test performance.

At 25°C

### pH range: 6.5–8.5

Specified design outlet-water range.

Outlet-water criterion

### Turbidity: 3 NTU

Design value supplied for process selection.

At 25°C

### Conductivity: 400 μS/cm

Specified electrical-conductivity design value.

Outlet-water criterion

### Total iron: 0.3 mg/L

Specified total-iron design value.

As CaCO₃

### Calcium hardness: 100 mg/L

Specified calcium-hardness design value.

As CaCO₃

### Total alkalinity: 200 mg/L

Specified total-alkalinity design value.

03

Turnkey delivery path

## One delivery chain connected the first water-quality requirement to final operation.

EFMC organized the project as a continuous engineering and delivery sequence. Each stage produced the conditions needed by the next, reducing gaps between design documents, fabricated equipment, site interfaces and operating logic.

01Turnkey project stage

**Define requirements** Translate the client’s water-quality criteria, cooling demand and site interfaces into a coordinated design basis.**›**

02Turnkey project stage

**Engineer the system** Develop treatment process, equipment layout, electrical distribution, control architecture, civil works and piping together.**›**

03Turnkey project stage

**Fabricate and assemble** Build treatment skids and automation panels against the approved interfaces before site installation.**›**

04Turnkey project stage

**Construct on site** Execute the treatment workshop, electrical and control installation, piping works and data-center-side construction.**›**

05Turnkey project stage

**Integrate and commission** Connect field equipment, instruments, PLC logic and supervisory screens, then verify operation as one system.**›**

06Turnkey project stage

**Run and hand over** Place the completed installation into operation and hand over a visible, controllable and maintainable water-treatment plant.

![Completed cooling-water treatment workshop for an AI data center](/api/media/file/%E5%AE%8C%E5%B7%A5%E7%85%A7%E7%89%87-%E8%BD%A6%E9%97%B41-1280x960.webp)

04

Integrated engineering

## Process, layout, power, controls and fabrication were resolved as one engineered system.

The design package coordinated plant footprint, equipment arrangement, main electrical circuits and automation interfaces before work moved to the site. Fabrication then followed the same system boundaries used in the drawings.

![Early CAD layout for the cooling-water treatment workshop](/api/media/file/%E5%88%9D%E6%9C%9F-%E5%9B%BE%E7%BA%B8%E8%AE%BE%E8%AE%A1-1280x657.webp)

01 / General arrangement

### Plant Layout and Equipment Footprints

Equipment, tanks, operating clearances and service areas were coordinated in the workshop layout before construction.

![Main-circuit electrical drawing for the treatment system distribution cabinet](/api/media/file/%E5%88%9D%E6%9C%9F-%E7%94%B5%E6%B0%94%E5%8F%8A%E8%87%AA%E6%8E%A7%E5%9B%BE%E7%BA%B8-640x480.webp)

02 / Electrical automation

### Power Distribution and Control Design

Pumps, treatment equipment and auxiliary systems were incorporated into a documented electrical and automation architecture.

![Water-treatment process skid during fabrication and assembly](/api/media/file/%E8%AE%BE%E5%A4%87%E5%88%B6%E4%BD%9C-640x480.webp)

03 / Equipment fabrication

### Process Skid Fabrication

Membrane housings, pumps, valves and manifolds were assembled as maintainable process units before delivery.

![Electrical automation cabinet during panel fabrication](/api/media/file/%E7%94%B5%E6%B0%94%E8%87%AA%E5%8A%A8%E6%8E%A7%E6%9F%9C%E5%88%B6%E4%BD%9C-1280x2841.webp)

04 / Panel assembly

### Automation Panel Assembly

Distribution, control and signal components were organized into the panel that would connect field devices with supervisory control.

05

Data-center-side construction

## The treatment plant was connected to real cooling infrastructure, not delivered as an isolated package.

Site work extended beyond the treatment workshop. Pipe routes, terminal connections and heat-rejection equipment on the AI compute side had to align with the water plant, construction sequence and final control strategy.

![Outdoor heat-rejection equipment installed for the AI data center](/api/media/file/%E6%96%BD%E5%B7%A5%E9%98%B6%E6%AE%B5-AU%E7%AE%97%E5%8A%9B%E4%B8%AD%E5%BF%83%E6%96%BD%E5%B7%A53.webp)

One delivery scope connected water preparation, compute-side circulation and rooftop heat rejection.

06

Completed treatment plant

## Each subsystem was completed as part of one maintainable water-treatment workshop.

The finished installation brings pretreatment, ultrafiltration, reverse osmosis, dosing, chemical cleaning, pumping and operations into a coordinated plant environment with clear access around major equipment.

![Completed ultrafiltration membrane system in the treatment workshop](/api/media/file/%E5%AE%8C%E5%B7%A5%E7%85%A7%E7%89%87-%E8%B6%85%E6%BB%A4%E7%B3%BB%E7%BB%9F-640x480.webp)

01 / Ultrafiltration

### Ultrafiltration Train

Parallel membrane modules form the front-end separation stage and connect to automated production and cleaning routes.

![Completed reverse-osmosis system with pressure vessels and pumps](/api/media/file/%E5%AE%8C%E5%B7%A5%E7%85%A7%E7%89%87-%E5%8F%8D%E6%B8%97%E9%80%8F%E7%B3%BB%E7%BB%9F-640x480.webp)

02 / Reverse osmosis

### Reverse-Osmosis Treatment

The RO stage follows ultrafiltration and provides the principal dissolved-solids treatment step in the documented process.

![Completed chemical dosing tanks, metering pumps and pipework](/api/media/file/%E5%AE%8C%E5%B7%A5%E7%85%A7%E7%89%87-%E5%8A%A0%E8%8D%AF%E7%B3%BB%E7%BB%9F-640x480.webp)

03 / Dosing

### Integrated Chemical Dosing

Dedicated tanks and metering pumps support the chemical conditions required by the treatment and water-supply processes.

![Completed chemical-cleaning system, storage tank and pump group](/api/media/file/%E5%AE%8C%E5%B7%A5%E7%85%A7%E7%89%87-%E5%8C%96%E5%AD%A6%E6%B8%85%E6%B4%97%E7%B3%BB%E7%BB%9F%E5%8F%8A%E6%B3%B5%E7%BB%84-640x480.webp)

04 / Cleaning and pumping

### Cleaning and Pumping Support

Cleaning circuits and pump equipment were installed alongside the main trains to support operation and maintenance.

![Wide view of the completed and organized water-treatment workshop](/api/media/file/%E5%AE%8C%E5%B7%A5%E7%85%A7%E7%89%87-%E8%BD%A6%E9%97%B42-640x480.webp)

05 / Integrated workshop

### A Plant Built for Access

The completed workshop organizes major treatment units, circulation paths and maintenance access as a single operating environment.

07

Walkthrough

## The finished plant, walked end to end.

A single pass through the completed workshop — pretreatment, ultrafiltration, reverse osmosis and the dosing skid, in the order the water moves through them.

Pretreatment → Ultrafiltration → Reverse osmosis → Dosing → Supply

08

Supervisory automation

## Operators can see the complete process instead of managing separate equipment islands.

The supervisory system separates the process into ultrafiltration, reverse osmosis, dosing and supply views while keeping operating states visible on a shared status panel. Field devices, valves, pumps, tanks and key process readings are represented in the same control environment.

![Supervisory process screen for the ultrafiltration system](/api/media/file/%E4%B8%8A%E4%BD%8D%E6%9C%BA%E7%94%BB%E9%9D%A2-1-640x480.webp)

01 / Ultrafiltration view

### Production, Backwash and Tank Status

The screen presents the UF flow path, pump and valve states, water levels and selected operating values.

![Supervisory process screen for the two-stage reverse-osmosis system](/api/media/file/%E4%B8%8A%E4%BD%8D%E6%9C%BA%E7%94%BB%E9%9D%A2-2-640x480.webp)

02 / RO view

### Two-Stage RO Process Visibility

Operators can review feed conditions, membrane-stage routing, production flow, conductivity and tank status from one screen.

![Supervisory screen for chemical dosing tanks and metering pumps](/api/media/file/%E4%B8%8A%E4%BD%8D%E6%9C%BA%E7%94%BB%E9%9D%A2-3-640x480.webp)

03 / Dosing view

### Dosing Equipment Status

Dosing tanks, mixers and metering pumps are presented by process function, with automatic and manual states visible to operators.

![Supervisory screen for treated-water storage and external water supply](/api/media/file/%E4%B8%8A%E4%BD%8D%E6%9C%BA%E7%94%BB%E9%9D%A2-4-640x480.webp)

04 / Supply view

### Storage and External Supply

Tank levels, transfer pumps, external supply pressure and conductivity complete the visible path from treatment to use.

![Completed control room with the water-treatment supervisory system in operation](/api/media/file/%E5%AE%8C%E5%B7%A5%E7%85%A7%E7%89%87-%E4%B8%8A%E4%BD%8D%E7%B3%BB%E7%BB%9F-640x480.webp)

05 / Operations station

### A Working Operations Interface

The finished operations station places the integrated process display in the environment used for daily supervision.

Project outcome

## A cooling-water requirement became a complete, operating treatment system.

The completed scope combines the treatment workshop, UF and RO trains, chemical dosing, cleaning and pumping systems, electrical automation, supervisory visualization and data-center-side cooling connections. Because the package contains design criteria but no formal commissioning test report, this case describes the delivered architecture and visible operating system without adding unsupported performance claims. The result is a coordinated plant delivered around the client’s requirements rather than a collection of independently supplied components.

> From the first water-quality target to the final operating screen, one team remained responsible for the whole system.
