DONGLIN CONTROLSDONGLIN CONTROLSIndustrial Automation
Completed cooling-water treatment workshop for an AI data center
Water Treatment

Cooling Water Treatmentfor an AI data center.

Starting with the client’s outlet-water requirements, EFMC coordinated process engineering, electrical automation, civil and piping works, data-center-side interfaces, construction and commissioning as one turnkey cooling-water treatment project.

Water-quality-led designUF + RO processElectrical automationTurnkey integration
IndustryWater Treatment
12
Design water-quality indicators
4 disciplines
Integrated engineering scope
01

Client requirement

The project began with water quality, but it could not end with process equipment alone.

The client needed a complete cooling-water treatment system for an AI compute facility. The treatment process had to meet the specified outlet-water criteria and connect cleanly with power, controls, buildings, pipelines and the operating data center.

01

A defined water-quality basis

Twelve client-provided indicators established the design basis, covering pH, turbidity, conductivity, hardness, alkalinity, chloride, iron, sulfate, ammonia nitrogen, COD, bacteria and organic phosphorus.

02

Several disciplines, one interface

Process design, electrical automation, civil works and piping could not be developed as isolated packages; equipment footprints, utilities, signals and tie-in points had to agree before construction.

03

A system ready to operate

The required endpoint was not separate skids or drawings. It was an integrated installation that could be commissioned, monitored from the supervisory system and handed over as a working plant.

02

Design basis

Client water-quality criteria became engineering inputs, not a note added after design.

The supplied outlet-water schedule defined twelve parameters. The values below are selected design criteria from that schedule, not claims of field-test performance.

At 25°C

pH range: 6.5–8.5

Specified design outlet-water range.

Outlet-water criterion

Turbidity: 3 NTU

Design value supplied for process selection.

At 25°C

Conductivity: 400 μS/cm

Specified electrical-conductivity design value.

Outlet-water criterion

Total iron: 0.3 mg/L

Specified total-iron design value.

As CaCO₃

Calcium hardness: 100 mg/L

Specified calcium-hardness design value.

As CaCO₃

Total alkalinity: 200 mg/L

Specified total-alkalinity design value.

03

Turnkey delivery path

One delivery chain connected the first water-quality requirement to final operation.

EFMC organized the project as a continuous engineering and delivery sequence. Each stage produced the conditions needed by the next, reducing gaps between design documents, fabricated equipment, site interfaces and operating logic.

01
Define requirementsTranslate the client’s water-quality criteria, cooling demand and site interfaces into a coordinated design basis.
02
Engineer the systemDevelop treatment process, equipment layout, electrical distribution, control architecture, civil works and piping together.
03
Fabricate and assembleBuild treatment skids and automation panels against the approved interfaces before site installation.
04
Construct on siteExecute the treatment workshop, electrical and control installation, piping works and data-center-side construction.
05
Integrate and commissionConnect field equipment, instruments, PLC logic and supervisory screens, then verify operation as one system.
06
Run and hand overPlace the completed installation into operation and hand over a visible, controllable and maintainable water-treatment plant.
Completed cooling-water treatment workshop for an AI data center
04

Integrated engineering

Process, layout, power, controls and fabrication were resolved as one engineered system.

The design package coordinated plant footprint, equipment arrangement, main electrical circuits and automation interfaces before work moved to the site. Fabrication then followed the same system boundaries used in the drawings.

Early CAD layout for the cooling-water treatment workshop
01 / General arrangement

Plant Layout and Equipment Footprints

Equipment, tanks, operating clearances and service areas were coordinated in the workshop layout before construction.

Main-circuit electrical drawing for the treatment system distribution cabinet
02 / Electrical automation

Power Distribution and Control Design

Pumps, treatment equipment and auxiliary systems were incorporated into a documented electrical and automation architecture.

Water-treatment process skid during fabrication and assembly
03 / Equipment fabrication

Process Skid Fabrication

Membrane housings, pumps, valves and manifolds were assembled as maintainable process units before delivery.

Electrical automation cabinet during panel fabrication
04 / Panel assembly

Automation Panel Assembly

Distribution, control and signal components were organized into the panel that would connect field devices with supervisory control.

05

Data-center-side construction

The treatment plant was connected to real cooling infrastructure, not delivered as an isolated package.

Site work extended beyond the treatment workshop. Pipe routes, terminal connections and heat-rejection equipment on the AI compute side had to align with the water plant, construction sequence and final control strategy.

Outdoor heat-rejection equipment installed for the AI data center
One delivery scope connected water preparation, compute-side circulation and rooftop heat rejection.
06

Completed treatment plant

Each subsystem was completed as part of one maintainable water-treatment workshop.

The finished installation brings pretreatment, ultrafiltration, reverse osmosis, dosing, chemical cleaning, pumping and operations into a coordinated plant environment with clear access around major equipment.

Completed ultrafiltration membrane system in the treatment workshop
01 / Ultrafiltration

Ultrafiltration Train

Parallel membrane modules form the front-end separation stage and connect to automated production and cleaning routes.

Completed reverse-osmosis system with pressure vessels and pumps
02 / Reverse osmosis

Reverse-Osmosis Treatment

The RO stage follows ultrafiltration and provides the principal dissolved-solids treatment step in the documented process.

Completed chemical dosing tanks, metering pumps and pipework
03 / Dosing

Integrated Chemical Dosing

Dedicated tanks and metering pumps support the chemical conditions required by the treatment and water-supply processes.

Completed chemical-cleaning system, storage tank and pump group
04 / Cleaning and pumping

Cleaning and Pumping Support

Cleaning circuits and pump equipment were installed alongside the main trains to support operation and maintenance.

Wide view of the completed and organized water-treatment workshop
05 / Integrated workshop

A Plant Built for Access

The completed workshop organizes major treatment units, circulation paths and maintenance access as a single operating environment.

07

Walkthrough

The finished plant, walked end to end.

A single pass through the completed workshop — pretreatment, ultrafiltration, reverse osmosis and the dosing skid, in the order the water moves through them.

Pretreatment → Ultrafiltration → Reverse osmosis → Dosing → Supply
08

Supervisory automation

Operators can see the complete process instead of managing separate equipment islands.

The supervisory system separates the process into ultrafiltration, reverse osmosis, dosing and supply views while keeping operating states visible on a shared status panel. Field devices, valves, pumps, tanks and key process readings are represented in the same control environment.

Supervisory process screen for the ultrafiltration system
01 / Ultrafiltration view

Production, Backwash and Tank Status

The screen presents the UF flow path, pump and valve states, water levels and selected operating values.

Supervisory process screen for the two-stage reverse-osmosis system
02 / RO view

Two-Stage RO Process Visibility

Operators can review feed conditions, membrane-stage routing, production flow, conductivity and tank status from one screen.

Supervisory screen for chemical dosing tanks and metering pumps
03 / Dosing view

Dosing Equipment Status

Dosing tanks, mixers and metering pumps are presented by process function, with automatic and manual states visible to operators.

Supervisory screen for treated-water storage and external water supply
04 / Supply view

Storage and External Supply

Tank levels, transfer pumps, external supply pressure and conductivity complete the visible path from treatment to use.

Completed control room with the water-treatment supervisory system in operation
05 / Operations station

A Working Operations Interface

The finished operations station places the integrated process display in the environment used for daily supervision.

Project outcome

A cooling-water requirement became a complete, operating treatment system.

The completed scope combines the treatment workshop, UF and RO trains, chemical dosing, cleaning and pumping systems, electrical automation, supervisory visualization and data-center-side cooling connections. Because the package contains design criteria but no formal commissioning test report, this case describes the delivered architecture and visible operating system without adding unsupported performance claims. The result is a coordinated plant delivered around the client’s requirements rather than a collection of independently supplied components.

From the first water-quality target to the final operating screen, one team remained responsible for the whole system.
WeChat
WhatsApp